Is there a way to get the change cycle time report to skip weekends in it’s calculations?

Hi,
I thought I saw somewhere a setting to get reports to skip weekends in calculations – for example in the change cycle time report I’d like it to skip weekends when it’s calculating how long it takes from one step to another.
I saw the one in preferences for reminders/escalations but don’t see one for reports.
Also, is there a way to get the report layouts to include the workflow tab or history tab?
Or is the only way to report that data from SQL or java report?

Thank you, 
Laura

Add Comment
1 Answer(s)

There is a setting in Admin to skip weekends under “Server Settings->Preferences”. But I am not sure whether the reports pay attention to it.

Agile Angel Answered on June 28, 2018.
Add Comment

Your Answer