It’s possible to change the default users calendar by import?

Agile User Asked on August 3, 2016 in Agile PLM (v9),   Product Collaboration.
Add Comment
3 Answer(s)

Hi Cyn, you can change default users calendar by import.Please refer to the attached file, it contain an Excel file as import example.
My best
Carlos

Agile Angel Answered on August 3, 2016.
Add Comment

Thanks Carlos, but if the user already existed its possible to change the calendar by import?

Agile User Answered on August 3, 2016.
Add Comment
Best answer

Definitely so, just change the value of the Default Calendar field in the Excel file to another existing one and use the import feature. The field  will be updated.
Nice and easy.

Carlos

Agile Angel Answered on August 3, 2016.