Mass BOM Changes – How To?
We are new to Agile PLM and we’ve created a number of BOMs for our products. Say for example we have a number of BOMs/products that use the same component/raw material just in different quantities. Now assume that raw material is getting changed to a different material and as a result has a different part number.
What’s the best most efficient way for users to make BOM changes/redlines in mass?
On the change order affected items tab there is a button labeled, “Bulk Change”. It will facilitate what you are looking to do: replace a part where it is used.