Hi Anyone please let me know how Dependencies tab work in PPM?

Hi Anyone please let me know how Dependencies tab work in PPM?

Agile User Asked on September 24, 2019 in Product Portfolio Management.
Add Comment
2 Answer(s)

Same as in MS Project. It drives scheduling. Think of it as an arrow between tasks. If the rule on the arrow is Finish-Start then the current task is scheduled to start when the dependent task is scheduled to complete.

Agile Angel Answered on September 27, 2019.
Add Comment

Thanks steves,

Can you please let usĀ  know the concept of Mileston in PPM?

Thanks,

Madhu

Agile User Answered on October 29, 2019.
Add Comment