When a Task is started on Friday after 5PM , it is starting on Saturday. Shouldnt it start on Monday?

1 Answer(s)

If I recall correctly, for PPM in 9.3.4 there is an option to set the work week to 5 days and different calendars.  Before that it is pretty much what you are seeing.  Others chime in if my recollection is missing some gaps.

Agile Angel Answered on August 19, 2015.