Changing Setting for DCOs

Currently we can only manage change for 1 document using a DCO. Is there a setting that can be changed to increase the capacity to manage several documents with one DCO?

Add Comment
5 Answer(s)

In general you have ability to create DCO with many document numbers.

 After You create new DCO process in status “Unassgined” do you success to add two document numbers?    

Agile Angel Answered on June 10, 2015.
Add Comment

No, we cannot add more than 1 document. If we do, the “Next Status” button is unavailable. We are using PLM 9.3.1.

Agile User Answered on June 14, 2015.
Add Comment

What is the criteria under  “Change Status” privileges for this workflow?

Agile Angel Answered on June 14, 2015.
Add Comment

Thanks for your reply, Hagi.

I have the systems analyst checking this setting. She is located in a different country so it may take a day or two for her to respond. In the meantime, is there anything else we should check, or are you certain the solution falls in the “Change Status” privilege for the DCO workflow?

Agile User Answered on June 15, 2015.
Add Comment

The problem need to be in “Change Status” privilege because you said  “Next Status” button is unavailable. 

Please update me what you find.

Agile Angel Answered on June 16, 2015.
Add Comment

Your Answer