Quality Analyst should have only rights to Modify the Plan Completion Date

Hi, 

Quality Analyst should have only rights to Modify the Plan Completion Date, How to do this?
I created the the modify privilege criteria is 
Corrective and Preventive Actions  $APPROVER Equal To Quality Analyst  

But Quality Analyst  is the user, here cant we use $APPROVER Equal To $QUALITYANALYST  like $USER.

Thanks
Divakar

Add Comment
1 Answer(s)

Hi, 

I found the Answer for this,
$APPROVER Equal To $QUALITYANALYST  like $USER is not possible.  

Create a Modify privilege for Plan Completion Date, Criteria goes like this  “Corrective and Preventive Actions  Cover Page.Status In CAPAs.Implementation “
Attach Modify Privilege to the Role “Analyst PQM”.

Thanks
Divakar

Agile Talent Answered on June 3, 2015.