PLM is adding approver on an ECO workflow status even though the particular status is skipped

On 9.3.3 PLM is adding approver on an ECO workflow status through the particular status is skipped. For ex, I have an ECO wf statuses as follows Status 1, Status 2 and Status 3. I have a workflow criteria which adds usergroup1 as approver. When I move the status from Status 1 to Status 3 directly, Status 2 is skipped but userroup1 is added as approver and showing awaiting approval. Do we have any fix for this?

Agile User Asked on October 22, 2019 in Product Collaboration.
Add Comment
5 Answer(s)

Can you add a screen capture… this doesn’t add up.  Would need to see a snapshot of the workflow page.

Agile Angel Answered on October 22, 2019.
Add Comment

Something more sinister maybe…. are you indicating that the ECO is at Status 3 yet showing the wf approval group from Status 2?  or did it stop @ Status 2?

Agile Angel Answered on October 22, 2019.
Add Comment

ECO is moved to Status 3 by Skipping Status 2. But Action on Status 2 is still showing Awaiting approval from Usergroup1.

Agile User Answered on October 22, 2019.
Add Comment

Is Usergroup1 a required approval, acknowledgement or notification?

Agile Angel Answered on October 22, 2019.
Add Comment

Yeap. UserGroup1 is added as approver through workflow criteria on Status2. The ECO which are undergoing through Status 2, will need an approval from Usergroup1.

Agile User Answered on October 22, 2019.